Mon, Jun 9, 2025The 09:00 OAC is the lever; the exposure sits in quote validity and scope.
Release three weeks of closeout. Anne’s single ruling on , , and releases the acoustic-ceiling closeout. The deck-drain answer is already carried into pricing.
Protect the commercial position. The $46,800 quote is one day beyond validity. Executed r2 §A.4 also assigns Calder Pools’ $84,000 heater package despite its claim under §3.7. Both responses are drafted for your review. Nothing has been sent.
Meetings ⓘ
09:00
OAC Meeting — change and closeout
Brief ready
14:00
Site coordination — concrete and steel
No brief · internal sync
Ball in Court
3 due today · 14 open · oldest 12d ⓘToday 5
CO-150Sign off the Calder Pools letter›
CRX-178Review Anne’s OAC cover note›
CO-148Approve the canopy-flashing change›
SUB-218Send the Atelier Vance nudge›
This week 8
RFI-138Roll the deck-drain answer into CRX-178›
Pour C3Chase Hatcher on heat 8/9 timing›
SUB-091Confirm the Z-bar retest, Brightwell›
RFI-142Confirm louvre free-area against design›
Show all 14⌄
Workflow snapshot ⓘ
Change Orders 10 open
2Your court3Pricing4Owner1Signing
Submittals 19 open
4Your court6Sub9Consultant
RFIs 6 open